November 19, 2007: insulation of the floor

The insulation of the floor is almost complete (3 weeks of work anyway): Remains partitions and doors to ask (2 or 3 days required).

In parallel, the developer began the work of connecting dry (EDF, Telecom, etc.) where the trench visible on the picture below.